404 Not Found
  • Violet Bank Trail

    The Violet Bank Trail project is within the existing 0.67 miles of Violet Bank Drive right-of-way and includes the construction of a sidewalk where it currently terminates on Kittery Drive, then transitions to the construction of a shared use path all the way to Selwood Drive.

  • Planning, Design & Development

    ​Project Details

    • VDOT TAP Grant Award in late 2018 with authorization to proceed granted in 2019

    • The Public Comment Period was held during the Spring of 2022. View detailed information about the Project, Environmental Documents, Project Drainage Report, and Public Outreach Report.

    • The project is currently under design.

    • The start of Construction is anticipated for 2023.

    • Completion of Construction anticipated for 2024.

    Violet Bank Trail Map